Lesson Learned



INTERNAL



No user selected

Report No.

406

Discipline/Origin

Drilling
No origin

Well

Shrek
6507/5-9 S, 6507/5-9 A

Date created

2020/03/13
2095 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Planning
Negative

Deepsea Nordkapp


Section N/A. What happened:
Vallourec – RfQ vs. Actual cost not comparable due to long lead time and spud date changes. Express shipment and 3rd party cost. Vallourec did not understood agreement and invoiced incorrectly

What Was Learned

Inform customer about changes in cost if spud date is changed
MSR to be reviewed by lead engineer and cost controller
No PO issued unless quoted prices are mutually understood (what is included in lump sum, and what will be charged outside)

What Actions Are Required

Inform customer about changes in cost if spud date is changed
MSR to be reviewed by lead engineer and cost controller
No PO issued unless quoted prices are mutually understood (what is included in lump sum, and what will be charged outside)